Symptom
The recommendation and supply/demand from recommendation are not displayed for future data in Step 6 of the MRP Wizard.
Reproducing the issue
You have a Bill of Materials (BoM) with several levels and long purchase lead times for the child items.
You run the MRP wizard and in Step 2 you choose an End Date that ends before the Lead Time of the child item/s is reached.
The Future Data Remarks show as 'Theoretical Recommendation'.
Solution
When the requested production time cannot be fulfilled within the planning horizon and system displays Future Data information, you can do the following.
- Show the recommendation in future data. The remark in pegging information is ‘Theoretical Recommendation’.
- Show the supply/demand from recommendation in future data. The remark in pegging information is ‘Supply/Demand from Theoretical Recommendation'.
- To get the recommendation for these data change the End Date in Step 2 of the MRP Wizard to meet the lead time of the BoM child item/s.